Inauguration Day Impacts

Inauguration Day Impacts


The inauguration of the 17th president of the University of Utah, Taylor R. Randall will be held on Wednesday, March 23, at 4:30 p.m. in Kingsbury Hall.

Visitors attending the event may ride UTA TRAX to the Stadium Station or park in the Stadium Lot. From here, attendees may ride the Campus Shuttle directly to Kingsbury Hall. Visitors unfamiliar with campus can also utilize the Campus Map to get walking directions and find bicycle parking near the venue.

On the event day, March 23, faculty, staff and students are encouraged to avoid bringing their vehicle to campus and ride public transportation for free instead. However, those who must drive to campus should prepare for traffic congestion on University Street and limited parking in the Stadium Lot and lots surrounding the Presidents Circle area, including the Northwest Garage, Naval Science Lot and more.

 

For more information about the transportation impacts and options available during the inauguration, call the Commuter Services Information Center at (801) 581-6415.

Huntsman Cancer Institute Cyclotron Construction

Huntsman Cancer Institute Cyclotron Construction


The Huntsman Cancer Institute (HCI) cyclotron facility will undergo construction from mid-March 2022 to spring 2023. During this period, pedestrian, bicycle and vehicular traffic will be diverted around construction zones with alternate routing. Please read signage carefully when traveling through and around the construction zone.

Timeline: March 2022 - April 2023: 

  • Mid-March: Jacobsen Construction begins installing site perimeter fencing and controls for stormwater pollution prevention
  • Mid-March: Construction begins with phased site utility work; total duration approximately one month
  • March 2022—March 2023: Facility construction
  • March—April 2023: Move-in and occupancy